A 2.3-mile paved trail with bridges, creek diversions and 17 retaining walls.

Location
Roseville, CA
Market
Water / Wastewater
Client / type
Multi-use trail and creek corridor
2.3 miPaved multi-use trail
3Prefabricated truss bridges installed
17Retaining walls (CIP, gabion, soldier pile, hybrid)

The project

Scope included a 2.3-mile paved multi-use trail, tree removal, three prefabricated truss bridge installations and two bridge modifications, and two creek bypass diversions.

The team built 17 retaining walls (11 cast-in-place, 2 gabion, 2 soldier pile and 2 hybrid), 14 RCP drainage systems and rock slope protection — plus a trailhead parking lot and restroom and two exercise areas.

Have a project out to bid?

Send plans, specs and the bid date to our estimating team.

Work with us

Let’s build what’s next.

Owners, agencies and general contractors: send bid invitations and project inquiries to our estimating team.